A metals manufacturer faked test results and provided faulty materials to NASA, causing more than $700 million in losses and two failed satellite launch missions, according to an investigation by the U.S. space agency. ...
The bad parts were used in the making of Taurus XL, a rocket that was supposed to deliver satellites studying the Earth's climate during missions carried out in 2009 and 2011. The launch vehicle's fairing, a clamshell structure that carries the satellite as it travels through the atmosphere, didn't fully open, causing the unsuccessful launch, according to a statement from NASA.
"When testing results are altered and certifications are provided falsely, missions fail," said Jim Norman, director for launch services at NASA in Washington.
-- David Stringer in Bloomberg, 30 April 2019